Begin Main Content Area

Oliver Road Intersection Improvement Project



Project Overview

The Oliver Road Intersection Improvement Project includes the construction of a five-leg roundabout at the intersections of Oliver (Route 4008), Flower, and Hamot (Route 4010) roads in Summit Township, Erie County. 

The intersection safety improvement project was created to address concerns raised by data gathered from 2012 to 2016 and studies conducted in 2019, which showed that crash rates at this intersection were over two times the statewide average for similar roadways and that the intersection geometry contributed to a large percentage of these crashes.

The two-year project includes removal of the existing intersections and construction of roundabout. Additional work includes milling and paving intersecting roads, construction of sidewalks, ADA curb ramps, drainage improvements, environmental mitigation, lighting, vegetation replacement, and pavement markings. Work will be done in seven phases and various detours will be in place during those phases.

In 2021, work was done offline of the current intersection. This included new alignments of Flower and the north portion of Hamot Road, new roadway approaches, drainage, sidewalks, highway lighting and concrete islands.

Work in 2022 will start with Phase 1B . Various detours will be needed throughout the summer. See the phases below for details on each anticipated detour.

The roundabout is expected to be fully opened to traffic in October 2022.

Oliver Road Roundabout2.jpg

Project Phases

Phase 1A - COMPLETED
Will include the construction of the offline portion of the roundabout and the offline portion of the new alignments of Flower and Hamot roads. Work also includes new roadway approaches, drainage, sidewalks, and concrete islands. Work is expected to be completed in the 2021 construction season.

Phase 1B - COMPLETED
Will focus on the Hamot Road north approach to the new roadway and the removal of the unused portion of Hamot Road. Temporary lanes will be constructed for two-lane traffic on Hamot Road. Additional drainage work will also be done. Traffic on Hamot Road will be detoured using Route 19 (Peach Street) and Hershey Road.  The detour is expected to be in place May 10. Work is expected to take approximately eight to nine days.

Phase 2A - COMPLETED
Will include the construction of the approach on Oliver Road, as well as drainage, sidewalks, and concrete islands. Traffic will use the temporary lanes on Hamot Road. Work is expected to take approximately 12 days to complete.

Phase 2B - COMPLETED
Will include the tie-in between Oliver Road approach and the new roadway. Work will also include the removal of a portion of the existing Oliver Road as well as drainage and sidewalks. Oliver Road traffic will be detoured using Hamot Road, Hershey Road, and Route 19. Work is expected to take approximately 11 days.

Phase 3 - COMPLETED
Will include the construction of the tie-in between Flower Road approach and new roadway. Work will also include the removal of a portion of the existing Flower Road as well as drainage and sidewalks. Flower Road traffic will be detoured using the Oliver Road, Dunn Valley Road (Route 4013), and Reichert Road (Route 4013). Work is expected to take approximately 15 days. 

Phase 4 - COMPLETED
Work will include removing another portion of the existing Oliver Road approach and construction of the tie-in between the Oliver Road and the new roadway. Traffic on Oliver Road and Hamot Road will be detoured using Flower Road, Reichert Road, and Dunn Valley Road. Work is expected to take approximately 13 days.

Phase 5
Will include constructing a tie-in between the south Hamot Road approach and the new roadway. Work will require varying detours between Oliver Road and Hamot Road.  Drivers should be alert for changing traffic patterns and detour signs. Work is expected to take approximately 10 days to complete. 

Phase 6
Will include constructing the central island including the truck apron, curbs and landscaping. Work is expected to take approximately 28 days to complete. 

Phase 7
Will include milling and paving the final surface for the roundabout lanes, as well as sign installation. 

Oliver Rd Roundabout2 7-9-21.JPG

Project Updates

8-11-22

​A portion of Hamot Road will be closed at the intersection with Oliver Road and Flower Road (Route 4008) due to the construction of the five-leg roundabout n Summit Township, Erie County.

The southern Hamot Road leg will be closed starting Monday, August 15 and is expected to reopen in 10 days. A five-mile detour will be posted using Flower Road, Reichert Road, and Dunn Valley Road

The southern Oliver Road leg is expected to reopen August 12, 2022.

7-29-22

A portion of Oliver Road is closed at the intersection with Hamot Road and Flower Road (Route 4008) due to a construction of the five-leg roundabout n Summit Township, Erie County,

The southern Oliver Road leg will be closed starting Monday, August 1 and is expected to reopen in 13 days. 

7-11-22

A portion of Flower Road (Route 4008) and the Flower Road entrance to the Erie County Technical School will be closed starting July 13 as work continues on the five-leg roundabout in Summit Township, Erie County.

Flower Road will be closed at the intersection with Hamot Road and Oliver Road. A 4.5-mile detour will be posted using Reichert Road (Route 4013), Dunn Valley Road (Route 4013), and Oliver Road. It is expected to be in place for 15 days, weather permitting. 

6-28-22

Oliver Road will be closed at the intersection with Hamot Road and Flower Road starting July 5, 2022. A five-mile detour will be posted using Route 19 (Peach Street), Hershey Road (Route 4010) and Hamot Road. It is expected to be in place for 11 days, weather permitting. 

4-29-22

Work on Phase 1B, started April 11, 2022, weather permitting. Various detours will be needed throughout the summer. The first is anticipated to be in place on May 10, 2022. See the phases above for details on each anticipated detour.

11-10-21

Work on the project is wrapping up for the 2021 construction season. The project will restart on Phase 1B in April 2022, weather permitting. 

6-9-21

Construction at the intersection improvement project at the intersection of Oliver Road, Flower Road, and Hamot Road in Summit Township, Erie County is scheduled to begin June 21, 2021 weather permitting and is expected to be completed by July 2022.

Motorists may encounter lane restrictions with traffic controlled by flaggers. Drivers should be alert for traffic pattern shifts and lane restrictions and should anticipate travel delays during active work hours.