SR 1005/720 Valley St. / Electric Ave
This project is for the highway restoration and resurfacing of SR 1005 in Lewistown. Construction includes waterline and utility relocation, full-depth reconstruction of Valley Street between Dorcus Street and Walnut Street, retaining wall, drainage improvements, inlets, manholes, concrete piping, sidewalks, curbing, ADA curb ramps, pavement markings, and miscellaneous items. - Electric Ave Detour Map

- Construction will be performed under a one-way detour for southbound traffic, using SR1005, SR 3003, SR 1017, and SR 22EB/Dorcus St.
- Completion expected 08/13/2024.
- Project Cost: $5.4 Million
|