Early August Update for Local Interchange Project in Centre County

08/09/2021

Bellefonte, PA – The Pennsylvania Department of Transportation (PennDOT) is providing an early August update for its Local Interchange/Route 26 project in Centre County. The work zone is located along I-80 near the Bellefonte/161 interchange and work to build the local interchange impacts traffic flow on Interstate 80.  

Currently, traffic control features the following:

On Wednesday, August 11, the next phase of construction on I-80 westbound will get underway. The contractor will implement a lane closure on the westbound mainline in order to perform line painting. All traffic traveling westbound will be directed to use the crossover lane. Hours for this work are 7:00 AM to 6:00 PM. After the line painting is completed, both lanes will be restored. 

On eastbound I-80, a double-lane shift to the right continues with concrete barrier in place. Traffic is shifted to the right lane and outside shoulder. This is a long-term set-up that will be in place through the summer.

Except for Wednesday, August 11, on westbound I-80, traffic continues to use the right/travel lane, with the left-travel lane crossing over to use an eastbound lane. Concrete barrier will be in place to separate east and westbound traffic in this configuration. The left lane will shift back to the right and the crossover lane will rejoin westbound at the end of the work zone. 


Work this season includes completion of basin construction in the median, completion of northern ramps, full depth reconstruction of I-80 westbound bridge piers and northern abutment, and construction of the connector road between I-80 and Route 26. 

The I-80/Route 26 local interchange project is east of Bellefonte and is part of a long-awaited safety-improvement in Centre County. HRI, Inc. of State College is the contractor on this $52 million project, which will run through October of 2022. Up-to-date information can be found on the project page at www.penndot.gov/jacksonvilleroad

The local interchange project is the first phase of a three-phase project to build local access, a high-speed interchange connection between I-99 and I-80, and to make improvements on Jacksonville Road. An initial $35 million for the project was announced in July 2018, coming through a federal Infrastructure for Rebuilding America (INFRA) grant. Completion of all three phases will support regional freight economy and improve the reliability of roadway travel throughout the region.

Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras. 

511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional Twitter alerts accessible on the 511PA website.

Subscribe to PennDOT news in Cameron, Centre, Clearfield, Clinton, Elk, Juniata, McKean, Mifflin, and Potter counties at www.penndot.gov/District2

For regional updates on Twitter, follow www.twitter.com/511PAStateCOLL.
MEDIA CONTACT:  Marla Fannin (814) 765-0423

# # #