- Scope: Resurfacing, Structure Rehab and Replacement, Drainage and Guiderail Upgrades
- Detour Length: 10 miles (Exit 163 (Amaranth) eastbound
- Construction Timeframe: April 2023 - August 2027
- Anticipated Detour Implementation Date: June 2024
- Anticipated Date Detour to be Lifted: August 2024
- Contractor: New Enterprise Stone & Lime Co., Inc.
- Current Contract: $30,990,126
View the I-70 Amaranth to Maryland State Line Project Detour Map (PDF).
- Scope: Repalce RC Arch w/Precast RC Box Culvert & Bethel Church Road Intersection Improvements
- Detour Length: U.S. 522 detour 16.2 miles, 7-day max; T-328 Bethel Church Road detour 12.6 miles, 58-day max.
- Anticipated Detour Implementation Dates: U.S. 522 June 2024, T-328 Bethel Church Road June - August 2024
- Construction Timeframe: January 2024 - Auust 2024
- Contractor: Charles J. Merlo, Inc.
- Currrent Contract: $1,413,000
View the U.S. 522 White Oak Run Project Detour Maps (PDF).