PennDOT to Begin U.S. 1 Widening, Improvement Project in Kennett, East Marlborough Townships

03/03/2023

King of Prussia, PA – The Pennsylvania Department of Transportation (PennDOT) announced today that preliminary construction will begin next week on a $10.4 million project to widen and improve a 1.3-mile section of U.S. 1 (Baltimore Pike) from the Kennett Oxford Bypass to Greenwood Road in Kennett and East Marlborough townships, Chester County.

Under this project, PennDOT's contractor will mill and overlay U.S. 1 (Baltimore Pike); construct a third travel lane on certain sections of U.S. 1 (Baltimore Pike) in each direction and use existing shoulders and right turn lanes to create a third lane for the rest of the corridor; build sidewalks along the north side of U.S. 1 (Baltimore Pike) from Schoolhouse Road to the Longwood Village Shopping Center entrance; eliminate the left turn movement from Orchard Avenue onto U.S. 1 (Baltimore Pike); install two new Dynamic Message Signs; and upgrade five signalized intersections within the corridor.

The purpose of this project is to improve capacity and the safe movement of vehicles through this heavily traveled section of U.S. 1 (Baltimore Pike) that includes commercial and residential development.

During construction, there will be periodic daytime and nighttime lane closures on U.S. 1 (Baltimore Pike) and at various intersections within the corridor during off-peak travel times to minimize travel impacts to motorists.

Beginning Monday, March 6, through Wednesday, May 31, from 9:00 AM to 3:00 PM, a weekday lane closure will be in place on northbound U.S. 1 (Baltimore Pike) between Orchard Avenue and Greenwood Road in East Marlborough Township, for PECO utility construction. 

Motorists are advised to allow extra time when traveling through the work area because backups and delays may occur. All scheduled activities are weather dependent.

Allan Myers, LP, of Worcester, Montgomery County, is the general contractor on this project, which is financed with 100% federal funds. Work on the entire project is expected to finish in late 2025.

Motorists can check conditions on more than 40,000 roadway miles, including color-coded winter conditions on 2,900 miles, by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information and access to more than 1,000 traffic cameras.

For a complete list of construction projects impacting state-owned highways in Bucks, Chester, Delaware, Montgomery and Philadelphia counties, visit the District 6 Traffic Bulletin.

Information about infrastructure in District 6, including completed work and significant projects, is available at www.penndot.pa.gov/D6Results. Find PennDOT's planned and active construction projects at www.projects.penndot.gov

Subscribe to PennDOT District 6 news and traffic alerts at www.penndot.pa.gov/District6.