Begin Main Content Area

Project Overview

​​The pavement along Bradford County Route 199-010 has reached the end of its viable life and needs to be replaced. The project located in Athens and Sayre Boroughs, Bradford County, begins at the northern side of the Norfolk Southern Railroad Tracks (Agway) on Route 199 and goes to the end of Route 199 at the New York State Line. This work is a reconstruction project including new curbing, ADA accommodations at the intersections, where appropriate, improved drainage, signal upgrades at three intersections, and some utility upgrades.

The project was let in 2020 and will take approximately four years to construct. The project will be constructed, for the most part, in half widths with the southbound direction using Route 199 throughout and the northbound direction will be detoured onto various routes as the construction phases progress. More detailed traffic schematics can be found on the right pane under resources.

PennDOT's team consisted of project management personnel, traffic specialists, municipal services, and consultants who collectively developed the project.

During public outreach, all public officials were contacted and invited to attend the meetings including police, hospitals, schools, emergency services, government officials, businesses, residents, etc.

Virtual Public Meeting

2024 Virtual Public Meeting

A virtual public meeting for the Route 199 Reconstruction Project will be held on Thursday, March 21, 2024, at 4:00 PM.  The meeting can be found by clicking the link below or by calling the numbers listed. 

Microsoft Teams meeting

Click the link below to join the meeting.

https://rb.gy/x08s4uOpens In A New WindowOpens In A New Window

Or call in (audio only)

+1 631-339-0571   United States, Brentwood (Toll)

(877) 284-0719   United States (Toll-free)

Conference ID: 905 280 156#​



2023 Virtual Public Meeting

A virtual public meeting for the Route 199 Reconstruction Project was held on Thursday, March 23, 2023, at 4:00 PM. ​​

The virtual public meeting held March 23, 2023 can be viewed below. 

 Content Editor

 


Project Contact

Primary Contact  - Construction Inspector Supervisor

Lake Thomas I lakthomas@pa.gov 

Phone: 570-971-9832


Secondary Contact - Project Manager

Kevin Lehman I kevlehman@pa.gov

Phone: 570-916-4068


Construction Project Manager

Kevin Smith | kevinsmith@pa.gov

Phone: 570.368.4231

 

Customer/ Media

Maggie Baker | magbaker@pa.gov

Phone: 570.368.4202


Design Project Manager

Rebecca Jackson  | rebeccjack@pa.gov

Phone: 570-368-4391

 

Sign up for Press Releases Please Visit

District 3 (pa.gov)


Project Statistics

Contract Cost: $16,426,020

Percentage Complete: 79%

Primary Contractor: Kriger Construction, Inc.

Detour Information

​See Resources