Atherton Street Work Schedule for Week of April 22

04/19/2024

Clearfield, PA – The Pennsylvania Department of Transportation (PennDOT) updated drivers on the schedule for its South Atherton Street (Route 3014) project that stretches from Curtin Road to just north of Westerly Parkway in State College. Motorists traveling through the work zone can expect the following the week of April 22. 

Crews will continue to install drainage pipe and complete full depth roadway reconstruction between Center Lane and West Irvin Avenue. The contractor will work from 7:00 AM to 5:00 PM daily, but drivers should expect to encounter flaggers in the roadway providing traffic control at the Westerly Parkway intersection between the hours of 9:00 AM and 3:00 PM throughout the week. PennDOT urges motorists to consider alternate routes if possible as traffic congestion is expected while the contractor is engaged in paving operations. 

The contractor will keep one lane of traffic open in each direction when they are not working. It will also maintain a pedestrian detour at and around the Westerly Parkway intersection throughout the week. 

PennDOT expects the traffic to be reduced to a single lane in each direction between West Irvin Avenue and Center Lane until early June while the contractor completes drainage improvements through the work zone. 

PennDOT urges motorists to pay attention to work zone and directional signage to enhance safety and keep traffic moving efficiently. Message boards alerting motorists to the construction zone and changing traffic patterns remain in place. 

PennDOT posts updates and detour information on the Atherton Street project page weekly and encourages drivers to visit the page at www.penndot.pa.gov/AthertonStreet

Overall work on the project includes roadway reconstruction, drainage improvements that include pipes and inlets, water and sewer lines, concrete curbing, sidewalks and detectable warning surfaces, pavement markings, traffic signals and supports, and miscellaneous items. HRI, Inc. of State College is the contractor on this $30.7 million project. PennDOT anticipates the contractor completing the project in the fall of 2024, but all work is weather and schedule dependent. 

PennDOT reminds motorists that intermittent traffic stops are possible for short periods during work activities and urges drivers to use caution when traveling through the work zone. PennDOT also reminds drivers not to follow construction equipment into the closed lane and to use both lanes to the merge point to minimize traffic back-ups and shorten travel delays when approaching the work zone. 

Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information, and access to more than 1,000 traffic cameras. 

511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following local alerts on X. 

Subscribe to PennDOT news in Cameron, Centre, Clearfield, Clinton, Elk, Juniata, McKean, Mifflin, and Potter counties at www.penndot.gov/District2

Follow PennDOT on X and like the department on Facebook and Instagram.

 ​# # #